| Based on observations
made during Hurricane Andrew, PUF/SPF roof systems appear
to have the potential to be excellent performers during
high-wind events. |
 |
The
October 1992 "Tech Transfer" article presented a preliminary
assessment of roof performance during Hurricane Andrew, which
struck South Florida on Aug 24, 1992. Following is a detailed
assessment of the wind performance of 11 spray-applied polyurethane
foam (PUF) roofs, which were inspected on August 29 and 30, and
on September 19 and 20.
Contour maps showing estimated wind speeds at 33 feet (10 m) above
grade have not yet been finalized. However, from damage observations
of surrounding buildings and trees, three of the PUF roofs were
in areas of very high winds, one was in an area of high winds
and seven were in areas of moderately high winds.
Some areas received extremely high winds, but no PUF roofs were
found in those areas. The following descriptions of buildings
are grouped in descending order of estimated wind speeds. Unless
noted otherwise, the roof slopes were about 1/4 inch per foot
(21 mm per m), or less. Also, unless noted otherwise, a metal-edge
flashing (gravel stop) was used at the perimeter.
Very
high winds
Building
68.
This is a two-story residence near Naranja,
with roofs on levels one and two. It sits in terrain Exposure
C (as defined by ANSI/ASCE 7-88, *1 and is about eight miles from
the coast.
The roof system is PUF, reportedly installed over a built-up roof
(BUR--mineral surface cap sheet, ply sheet and a nailed base sheet),
over wood planks. The PUF roof is approximately 10 years old.
A portion of the PUF roof apparently was blown off on parts of
the upper and lower roofs. At the time of inspection, temporary
repairs had been made. The entire second-level roof and a portion
of the lower roof had been covered with what appeared to be a
two-ply, built-up membrane with an aluminum coating. The nature
of the temporary repairs made investigative work difficult. The
lower roof consists of several separate sections. About half of
the main section occurs over a canopy that is open on three sides.
It appeared that the BUR/PUF composite roof over the canopy had
blown off, but apparently it did not progressively fail beyond
the canopy area (see . Photo 1). The metal-edge hashing had been
replaced along the canopy edge.
Beyond the canopy area, a piece of foam was missing at the metal-edge
flashing flange. This probably was caused by missile (i.e., windblown
debris) impact. The BUR/PUR roof did not progressively peel beyond
the impact area.
The other lower roofs are less than 100 square feet (9.3 meters
squared) each. These roofs were not damaged, except for some minor
missile damage. The building has an overhang of about 4 feet (1,200
mm) along one edge of the upper roof. As with the lower canopy,
it appeared that the BUR/PUF roof over the over-hang blew off.
But, as on level one, it did not appear to progressively fail
beyond the overhang.
Within about 200 feet (60 m) from the house, in different directions,
there are three other one-story buildings. One building is framed
with wood trusses. It experienced significant gable end wall failure
and collapse of several trusses. Several sheathing panels were
also blown-off, along with many asphalt shingles.
The second building has a hip roof that had been covered with
felt. The type of roof covering and the extent of damage was not
determined. The third building has a low-sloped roof. It was reported
that its BUR blew off. Although there are few trees nearby, several
were significantly damaged.
Building
20.
This is a one-story commercial building
near Cutler Ridge, composed of two intersecting domes. It sits
in terrain Exposure B and is about three miles, from the coast.
The roof system is PUF (self-flashed at the edge), presumably
over thin-shell concrete.
No missile damage or peeling of the PUF roof was observed. A television
antenna on the side of the domes was blown over, and a cowling
on a fan on top of the domes was blown off. A lack of buildings
within about 110 feet of the domes may be the reason for the lack
of missile damage.
Gable end wall failure of a wood truss-framed apartment building
west of the domes was observed. Several asphalt shingles were
blown off of these buildings.
Building 14.
This is a one-story house near Howard in
terrain Exposure B. The coast is about three miles to the east
and about two miles to the southeast. The roof system is PUF,
reportedly over a BUR. The roof slope is about 2·in·12. The PUF
roof is about 10 years old (see Photo 2).
The
only apparent damage to the PUF roof was minor missile damage
in several areas. One of the missiles was a piece of a tree limb
about 3/8 inch (10 mm) in diameter. Also, at the overhang, an
electrical conduit penetration for the power feeder had moved
back- and-forth, causing a hole. The homeowner reported no leaks.
This roof appeared to be easily repairable.
A garage roof (with a very low slope) joins the PUF roof. It is
covered with a mineral surface cap sheet. A portion of this roof
lifted at a corner and peeled. The base sheet was nailed to plywood,
but there were few nails. However, the failure appeared to be
related to the lack of attachment of the metal-edge flashing.
There was extensive tree damage in the area. It also appeared
that essentially all of the nearby houses experienced roof covering
problems. An aggregate-surfaced BUR (on a house similar to the
PUF house) apparently had problems along the rake, because it
was temporarily covered with felt. Some houses experienced a loss
of asphalt shingles, while others lost tiles.
High
winds
Building
56. This is a two-story condominium
near Kendale Lakes in terrain Exposure B. It is about 10.5 miles
(17 km) from the coast. The roof system-PUF over an existing BUR-has
a 14-inch (350-mm) parapet. Rather than having a coping, the parapet
was self-flashed with PUF. In the field of the roof, the foam
was covered by loose aggregate (similar to the type used for BUR).
Because of the aggregate surfacing, only the exposed portions
of the foam were coated. The PUF roof is about a year old.
An extensive area of the aggregate was scoured (blown away-see
Photo 3). However, because of the parapet, it appeared that little
(if any) aggregate had blown off of the roof. The only other damage
to the PUF roof was caused by missiles impacting the parapet and
equipment curbs. Some of this minor damage was caused by the aggregate,
and some was caused by pieces of BUR felt from another building.
The homeowner reported no leaks. With this minor damage, the roof
was easily repairable, with most of the work related to relocation
of the aggregate.
Tree damage in this area was light. Reportedly, some of the other
condominiums in this complex experienced problems with their roofs
(presumably BUR), but it did not appear that damage was widespread.
However, in another nearby condominium complex (of a different
design), it appeared that most of the BUR systems were damaged.
These buildings had metal-edge flashings, which appeared to be
the cause of the problem due to inadequate attachment. Also in
this neighborhood, there are several houses and condominiums roofed
with asphalt shingles or tiles. Performance of each type of covering
was variable; some roofs appeared to have little or no damage,
while others had extensive damage. The variability was likely
due to design, materials or application, rather than variations
in the wind field.
Moderately
high winds
Building
66.
This is a two-story hotel on the east side
of Miami Beach. It sits in terrain Exposure D (only a street and
the beach separate the hotel from the ocean). The roof system
is PUF over a BUR. The parapet height is about 32 inches (800
mm), and the top is self-flashed with PUF. The PUF roof is about
five years old. The only apparent damage to the PUF roof was caused
by missiles in several areas, including a portion of the parapet.
The damage was caused by the BUR and by wood framing from an adjacent
building. Some of the missiles landed on the PUF roof with fairly
great force. One caused a large gouge that was 7/8 inches (22
mm) deep. In another location (an area about 17 x 22 inches, or
425 x 550 mm), the latex (acrylic) coating peeled. The building
owner reported no leaks. This roof appeared to be easily repairable.
There are few trees in this area. Those on the ocean-side of the
hotel appeared to have little (if any) damage. Besides the damage
to the adjacent building's BUR, other roofing damage in this area
appeared to be light. However, most of the buildings have low-
slope roofs, so it was difficult to accurately judge surrounding
damage. From periodic piles of debris along the streets, occasional
BUR damage was surmised.
Building
67.
This is a vaulted· shaped church near West
Miami. The maximum roof height is about three stories. It sits
in terrain Exposure B, and the coast is about nine miles (15 km)
to the east and about six miles (10 km) to the southeast. The
roof system is PUF (self-flashed at the edge), presumably over
concrete. A two-story building, with a smooth-surface BUR, is
connected to the back of the vaulted structure. The PUF roof is
about one year old. It was not possible to gain access to the
top of the vaulted building, but no PUF damage was observed from
the second-level roof or from the ground. A recent patch was observed
on the BUR; it was about 6 x 10 feet (1.8 x 3 meters). It appeared
that a gutter had lifted and peeled the membrane. Tree damage
in this area was very light. A few of the houses in the neighborhood
had minor asphalt shingle and tile damage.
Building
72.
This is a tall, one-story warehouse near
Hialeah in terrain Exposure B. It is about eight-and-a-half miles
(14 km) from the east coast of Miami Beach. The roof system, a
PUF over BUR, is about eight years old. There was no apparent
damage to the PUF. Tree damage ill this area was minimal. A BUR
on an adjacent building (of slightly lower height) suffered some
damage. The extent of damage could not be determined, because
the entire roof had been replaced. Near to this building is Building
73 (described below).
Building 73.
This warehouse is two buildings away from Building 72. The two
buildings are about the same height. The roof system is PUF over
BUR. In one area, the PUF is about 3/4 inches (19 mm) thick. The
PUF is about 10 years old. At one corner, the metal-edge flashing
(including the nailer) and the BUR/PUF composite lifted and peeled.
The peeled area was about 20 x 45 feet (6 x 14 m-see Photo 4).
The nailer was attached to the concrete wall with cut nails, but
it was not possible to determine the spacing. In addition, there
were a few minor damaged areas due to missile impact. The peeled
area had been temporarily patched with a relatively thin layer
of uncoated PUF. This roof appeared to be easily repairable.
Adjacent
to this building is Building 74.
It is an aggregate surfaced BUR, with a
base sheet nailed to a lightweight insulating concrete deck (which
appeared to have perlite aggregate). It also peeled, near the
peel on Building 73 (Photo 4). The peeled area was about 20 x
40 feet (6 x 12 m), plus an additional strip 25 feet (8 m) beyond
the 40·foot (12-m) dimension. This strip varied in width from
about 2 to 5 feet (600 to 1,500 mm). The peel appeared to be caused
by lifting of the nailer to which the gutter and metal edge were
attached. It appeared that all of the base sheet fasteners remained
in the deck (which is typically the case with peeling with this
type of system). The nailer was fastened into the concrete walls
with cut nails at about 29 inches on center. At another corner,
a portion of the membrane and deck was missing. A 5-foot-long
(1,500mm) hole occurred in the deck between bulb tees. It appeared
that this was caused by impact of the BUR/PUF composite debris
from Building 79. Repair, rather than replacement, of the roof
on Building 74 would be possible. However, besides the difficulty
of tying in the new work to the existing, the exposed deck also
presents problems. At the time of the investigation, it had been
exposed for 27 days and subjected to a lot of rain. In addition,
there could be undetected damage to the membrane where the nailer/gutter/membrane
landed. In the vicinity of Buildings 72, 73 and 74, there are
several similar warehouse buildings. It appeared that most of
them have aggregate-surfaced BUR, and it appeared that most of
them had small membrane peels at corners. which were likely due
to inadequate attachment of the metal-edge flashing. The metal-edge
flashing on two of these other buildings was not cleated or face-fastened.
Building 75 This
is a tall, one-story warehouse a few blocks from Buildings 72,
73 and 74. It also is in terrain Exposure B; the roof system is
PUF over BUR. In the field of the roof, the foam is covered by
loose aggregate (similar to the type used for BUR). The PUF roof
is about one year old. There was no apparent damage, nor was there
any significant aggregate scour. Tree damage in this area was
minimal. There are two buildings behind this building, one with
a single story, and the other with two stories. The one-story
building had recently been re-roofed, but it was not possible
to determine the original type of roof covering. The two-story
building had flashing damage, and perhaps some peeling at a corner.
It appeared that it is covered with an aggregate-surfaced BUR.
Across the street from Building 75, there are three one-story
buildings. One roof had been replaced. On the other two, a portion
of each roof was peeled at a corner. These roofs appeared to be
aggregate-surfaced BUR. Another building beyond these buildings
was temporarily covered with a tarp. On the other side is Building
76, a warehouse of similar height to Building 75. This building
has an aggregate-surfaced BUR (membrane, wood fiberboard, nailed
ventilated base sheet) over a lightweight insulating concrete
deck (which appeared to have perlite aggregate). The metal-edge
flashing lifted at the corner and peeled the membrane. It has
an uncleated, 6·inch (150·mm) vertical face. A portion of the
nailer was rotted and some of the lightweight concrete adjacent
to the nailer was in poor condition. There was a hole about 12
x 18 inches (300 x 450 mm) through the membrane and deck several
feet from the roof edge. Perhaps this was caused by debris from
the peeled area. Around the hole, the deck appeared to be in poor
condition.
Building
69. This is a tall, one-story warehouse near Hialeah, a few miles
from the warehouses previously described. It sits in terrain Exposure
B, and is about 11 miles from the east coast of Miami Beach. The
roof system is PUF over BUR. The PUF is about 10 years old. There
was no apparent damage to the PUF. Behind this building is a building
of similar height with an aggregate-surfaced BUR. Scour was observed
at two corners. Adjacent to Building 69 is Building 70, as described
below.
Building 70. This building is about the same height as Building
69. The roof system is PUF over BUR (with a nailed base sheet)
over a lightweight insulating concrete deck (which appeared to
have perlite aggregate). In one area, the PUF is about 1 inch
(25 mm) thick. The PUF is about 11 years old. At one corner, the
metal-edge flashing and the BUR/PUF composite lifted and peeled.
A gutter occurs along one edge. At the other edge, the nailer
lifted with the flashing. The nailer was attached to the concrete
wall with cut nails. A portion of the nailer that remained attached
was rotted. The metal flashing is attached to the nailer with
1 1/4-inch (31·mm) nails spaced at 5, 6, 7 and 6 1/2 inches (125,
150, 175 and 163 mm). It has an uncleared 4-inch (100-mm) vertical
face and a 5·inch (75·mm) horizontal flange. The peeled area was
about 20x 30 feet (6 x 9 m--see Photo 5). The peel appeared to
be caused by lifting of the nailer along one side, and lifting
of the metal-edge flashing on the other side. The deteriorated
nailer probably played a key role in the failure. It appeared
that all of the base sheet fasteners remained in the deck.
Portions
of the deck were deteriorated along some of the bulb tees, and
in one area there were holes through the deck along a line perpendicular
to the tees (see Photo F,). These deck problems did not appear
to be related to the hurricane.
The
coating (polyurethane) is in poor condition, with foam exposed
over much of the roof (not related to the hurricane). Because
the foam has been exposed for an extended time, in several areas
much of it has weathered away. However, the foam was dry, except
for the cells near the surface. Across the street is a two-story
warehouse that has a smooth-surfaced BUR over perlite over an
aggregate-surfaced BUR (with a nailed base sheet). It was not
possible to get on this roof. However, from debris on the ground,
it appeared that a very large area of the roof had peeled.
Discussion
1.
It appears that if the substrate to which the PUF roof is applied
(e.g., BUR) lifts and peels, PUF plays a role in limiting the
size of the peel. Undoubtedly, PUF limited progressive peeling
failure on the second-level roof (and perhaps on the first level
roof) of Building 68. However, the extent of the peel on Building
73 (PUF) was not greatly smaller than the peel on Building 74
(BUR).
PUF's
ability to limit progressive failure is probably proportional
to its thickness. Two of the PUF roofs that peeled had thickness'
of about 1 inch (25 mm). By increasing the thickness to 2 inches
(50 mm), the area of peel could probably have been greatly reduced.
With this greater thickness, it is believed that the lifted portion
of the composite (e.g., BUR/PUF) would snap off near the roof
edge, or the lifted section would just drop down onto the deck.
Of course, if peeling occurs, it is advantageous to limit its
size to minimize water infiltration and the generation of missiles.
2.
Compared to BUR, modified bitumen or metal, PUF is more easily
damaged by missiles. However, the damage is probably easier to
visually find and easier to repair. PUF's greatest attribute regarding
missile damage is its ability to remain watertight, provided that
the missile does not fully penetrate the foam. It appears that
a thickness of about 2 inches (50mm) is sufficient to prevent
penetration of most missiles. PUF also does not appear to be susceptible
to progressive peeling after being struck by large missiles, unlike
a few other types of roof coverings.*2
3.
Scour of aggregate surfaced PUF (Building 56) does not present
a problem to the foam, provided that the aggregate is repositioned
within a few months. However, if the aggregate blows off of the
roof, it can cause damage to adjacent buildings and cars, and
it can cause injury. In high·wind environments, parapets are needed
to prevent aggregate blow-off. 4. Damage to many of the warehouse
roofs was probably related to the age of these buildings (which
could easily be more than 30 years). They were constructed with
some practices that are not recommended in high· wind environments,
such as using cut nails to attach the nailers to concrete, and
the use of uncleated metal-edge flashing. The deteriorated nailers
also probably played an important role, and illustrates the wisdom
of the recommendation to use preservative treated nailers.
Conclusions
Based
upon observations made during Hurricane Andrew, Hurricane Hugo
*3 and the 1990 Plainfield (Ill.) tornado, *4 it appears that
PUF roof systems have the potential to be performers during
highwind events. Besides being resistant to the wind loading,
PUF's high·wind attribute is in part due to its resistance to
progressive peeling failure due to missile impact, deck failure
or a lifting and peeling failure at the roof edge. PUF's ability
to resist water infiltration after being impacted by missiles
is also a great asset, particularly in an area that has been impacted
by a powerful hurricane, because emergency repairs may take weeks
or months.
Recommendations
1.
In high-wind environments, if the designer specifies an aggregate-surfaced
PUF roof, it is recommended that the potential for aggregate blow-off
be evaluated using the 1976 Kind and Wardlaw guide.)
2.
For metal-edge flashings, refer to the recommendations in the
1990 IJORT.*6 <
3.
If the designer specifies a PUF roof (or any other type of roof
covering) over an existing membrane, the designer should recommend
evaluation of the deck by an engineer if deck deterioration is
suspected.
4.
If the designer specifies a PUF roof over an existing membrane
in a highwind environment, a minimum foam thickness of 1.5 to
2 inches (38 to 50 mm), depending upon wind conditions, is recommended
to limit the extent of a possible peeling failure of the exiting
membrane. The reason for this conservative measure is that the
integrity/strength of the existing roof covering system will be
unknown to some extent.
5.
If the designer specifies a PUF roof over an existing membrane,
and if the designer decides to reuse the existing metal-edge flashing,
the vertical face should be evaluated by the designer. If it is
uncleated, if there is little interlock between the metal and
cleat or if the face can be deflected outward far enough to possibly
unlock the metal/cleat, then it is recommended that the metal
be fastened along its face or replaced. However, it should be
realized that if the metal is not replaced, it is very difficult
to know if the nailers are adequately attached or still in sound
condition.
References
1.
Minimum Design Loads for Buildings and Other Structures,
ANSI/ASCE 7-88, July 1990.
2.
Smith, Thomas L.. "Tech Transfer," Professional
Roofing, October 1992, page 58.
3.
McDonald, J.R. and Smith, T.L., Performance Of Roofing Systems
in Hurricane Hugo August 1990.
4.
NRCA unpublished research, August and September 1990.
5.
Kind, J.R. and Wardlaw, R.L., Design of Rooftops Against Gravel
Blow-off, National Research Council of Canada, Report No.
15544, September 1976.
6.
Smith, T.L., "Hurricane Hugo's Effects on Edge Flashing,"
International Journal of Roofing Technology, 1990, page
65.
Thomas
L. Smith is NRCA's director of technology and research.